Bid Recap
From burdened crew rate to sell price. Every layer on its correct base, in the order the recap sheet applies it.
Crew & burden
Composite $36.50/hr on a base of $29.29 · 7-person crew
| Class | Head | Base $/hr | Burdened |
|---|---|---|---|
| Foreman | $51.66 | ||
| Journeyman | $36.76 | ||
| Apprentice | $28.38 | ||
| Helper | — |
FICA 7.65% · FUTA 0.6% on $7k · TX SUTA 2.7% on $9k · GL 2% · small tools 2% applied automatically. Wages default to BLS OEWS May 2025, Houston open shop.
Direct cost
Indirects, risk & margin
Recap sheet
Direct
Direct labor$87,588.56
Direct material$86,000.00
Equipment rental$9,500.00
Subcontracts$24,000.00
Other direct$3,000.00
Field indirects
Supervision$8,758.86
Project management$8,403.54
Consumables$2,580.00
Permits & fees$1,200.00
Tax & time
Sales tax$7,095.00
Escalation$2,603.83
Total cost$240,729.79
Risk & margin
Contingency$7,221.89
Overhead$29,754.20
Profit$22,216.47
Insurance$3,076.13
Bond$4,614.19
Sell price$307,612.67
Net margin
7.2%
Gross margin
21.7%
Sell per MH
$128.17
Labor share of cost
40%
Productivity exposure
Planned profit$22,216.47
Profit after a 10% labor overrun$12,581.73
A 23.1% labor overrun erases all profit on this bid. Productivity factors on the estimate lines are where that risk is priced.